Structural alterations in office refurbishments: feasibility checks before design

Back to Insights

Structural alterations in office refurbishments: feasibility checks before design

Creating a new staircase, changing an atrium or opening up a floor can transform how an office works. Before developing the design, structural refurbishment requires a clear assessment of the existing building, the proposed intervention and how the works could be delivered.

A visually simple alteration can affect several interconnected systems. Structure, services, fire strategy, access and construction sequencing need to be considered together.

Early feasibility work helps establish whether the idea is viable, what information is missing and which design options deserve further investment.

Define the purpose of the structural alteration

Start with the operational or property outcome. You may want to connect teams across floors, improve circulation, increase usable space or adapt an area for a different function.

Describe that outcome before fixing the physical solution. A new staircase may be one response to disconnected teams, but its location and form need to be tested against the building.

Consider alternative interventions that could achieve the same objective. This creates a basis for comparing cost, disruption, carbon and delivery risk.

The feasibility brief should identify the essential result, the preferred concept and any assumptions that remain open.

Review the existing structural information

Gather available structural drawings, calculations, survey records and information about previous alterations. Establish what is known about the frame, floor construction and foundations where relevant.

Records can be incomplete or differ from the building as it now exists. The structural engineer should identify what needs verification.

An apparently redundant element may still contribute to stability or support an installation. Do not infer its function from appearance alone.

Create an information-gap schedule showing the investigation required, who will carry it out and how the findings could affect the design. This makes uncertainty visible before the programme becomes dependent on a particular solution.

Plan surveys and opening-up investigations

Surveys should be directed by the questions the design team needs answered.

The work may involve dimensional surveys, material investigation, checking reinforcement or reviewing connections and support conditions. The appropriate methods depend on the building and proposed alteration.

Intrusive work also needs to account for services and hazardous materials. A management asbestos survey should not simply be assumed adequate for planned intrusive refurbishment; obtain specialist advice on the survey required.

Agree access and any temporary vacancy requirements before investigations begin. Record limitations clearly so that an inaccessible area does not disappear from the risk register.

The objective is to reduce uncertainty systematically, not to commission surveys without a defined purpose.

Check load paths and the effect on adjoining areas

The structural engineer must assess how the proposed alteration changes the building’s behaviour.

An opening can affect the way loads are carried around a floor. New equipment or a change of use can introduce different loading. Removing or altering a staircase may affect access as well as the structure around it.

Review the surrounding areas, including occupied floors and neighbouring parts of the building. The impact is not necessarily confined to the outline of the proposed work.

A feasibility conclusion should identify the required strengthening or other measures, the assumptions behind them and any matters requiring further design.

Coordinate structure, services and fire strategy

Structural feasibility is only one part of the decision.

Interface Question to resolve
Building services Do ducts, pipes, cables or plant occupy the proposed area?
Fire strategy How does the change affect escape, separation and related systems?
Accessibility Will the revised arrangement support appropriate access and movement?
Architecture What happens to floor levels, ceilings, finishes and usable space?
Operations Can adjoining areas remain in use during the intervention?

For example, a staircase opening may be structurally possible but conflict with a major services route. Resolving the issue later can change both design and programme.

Arrange coordinated reviews while options are still flexible. A feasible solution should work as a whole, not only within one discipline.

Consider temporary works and construction sequence early

The completed design may be stable while the route to building it requires substantial temporary measures.

Consider how existing elements will be supported during removal, how materials will be brought in and how safe access will be maintained. Temporary works require appropriate engineering and coordination.

Discuss the intended sequence with the construction team. Available lifting routes, installation tolerances and space for equipment can influence the design.

Do not leave logistics until the main design is fixed. In a constrained building, the ability to install a component may be as important as its final position.

ODGroup project example: 42 Wigmore Street

At 42 Wigmore Street, structural work included replacing the central staircase and extending the atrium. An external temporary scaffold staircase maintained access during construction.

The project demonstrates why permanent design and temporary access need to be considered together. The method of delivery is part of the feasibility question, particularly when a building has limited circulation routes.

Contemporary bathroom with soft green walls, terrazzo vanity top, black round basins, and large circular mirrors with strap hangings, complemented by integrated LED lighting.

Establish approvals, budget and decision points

Ask the professional team to identify the approvals and agreements applicable to the proposed works. These may involve the landlord, building control, planning or other parties depending on the intervention.

Do not assume that an internal alteration has no approval implications. Equally, avoid treating every possible approval as applicable without a project-specific assessment.

Prepare a feasibility cost range that makes uncertainty visible. Separate investigations, permanent works, temporary measures, services changes and consequential finishes.

Set a decision point before detailed design proceeds. The client should understand the preferred option, alternatives, outstanding risks and the evidence needed to move forward.

Structural office refurbishment FAQs

Can we remove a wall if it does not appear load-bearing?

Appearance is not sufficient evidence. Its structural role, services and fire-related function need to be assessed by the appropriate professionals before removal is considered.

Can a new staircase be installed between office floors?

It may be possible, but feasibility depends on structure, layout, services, fire strategy, access and approvals. A coordinated investigation is needed before committing to a location or design.

Are original structural drawings enough?

They are valuable, but they may need verification against the existing building. Previous alterations and incomplete records can create differences that affect the proposal.

Can structural work take place in an occupied building?

Sometimes, with appropriate separation, engineering, sequencing and operational arrangements. The scope and risks must be assessed. Some activities may require temporary vacancy or restrictions.

When should a contractor be involved?

Early construction input can help test access, temporary arrangements and buildability while options remain open. The appointment and responsibilities should be appropriate to the procurement route.

Test structural ideas before committing to design

A good feasibility process turns an attractive concept into an informed decision about the building.

Explore ODGroup’s structural refurbishment service to discuss the intended alteration and the investigations needed to assess it.

 