How much does an office fit-out cost in London?

The cost of an office fit-out in London depends on the condition of the space you take on and the workplace you need to create. As a rough guide, published 2026 benchmarks put a conventional fit-out at around £70-£120 per sq ft, assuming the space already has suitable CAT A services. Please note, this is not an all-inclusive budget or an ODGroup quotation.
For a 10,000 sq ft office, that range equates to approximately £700,000–£1.2 million for construction. Furniture, technology, professional services and other client costs need to be assessed separately. A building requiring substantial services replacement or structural work needs a different cost plan.
The first question is therefore not simply how large your office will be. It is what you are starting with, and what needs to be ready on the day your team moves in.
Office fit-out costs per square foot: what the figures cover
A square-foot rate is useful when its assumptions match your project. It becomes misleading when a construction allowance is compared with a price that includes furniture, design, technology and relocation.
| Construction benchmark | Indicative rate | Construction allowance for 10,000 sq ft |
| Lower specification | £70 per sq ft | £700,000 |
| Mid specification | £90 per sq ft | £900,000 |
| Higher specification | £120 per sq ft | £1,200,000 |
These published market reference points assume a typical 10,000 sq ft office with the base building, CAT A power and heating, ventilation and air conditioning in good condition. They are not minimum or maximum prices. Confirm exclusions, fees, VAT and the measurement basis before using any benchmark in an approval paper.
Smaller projects may also have a different rate because site establishment and management costs are spread over less floor area.
How the handover condition affects your fit-out budget
An office described as CAT A will usually have a basic internal specification for the incoming occupier to adapt. A CAT A+ space may already contain meeting rooms, a kitchen and furniture. A CAT B fit-out is tailored to a business’s operational requirements.
The category alone does not establish what has been provided. Obtain the landlord’s specification, inspect the space and agree the handover condition.
A recently completed floor may still require changes to suit your layout and requirements. Adding enclosed rooms can affect ventilation, lighting, controls and fire protection. A fitted office may need fewer visible alterations but more technology work than expected.
Use the initial inspection to identify three things: what can be accepted as it stands, what needs adapting and what needs replacing. That distinction gives the cost plan a more reliable starting point.
What should a complete office fit-out budget include?
Prepare the total project budget around responsibilities, not just the building contract.
| Cost area | Questions to resolve |
| Design and professional team | Which appointments are included in the chosen procurement route? |
| Construction and services | Does the scope include strip-out, adaptations, finishes and commissioning? |
| Furniture | Are desks, chairs, storage and meeting furniture new, reused or supplied separately? |
| Technology | Who owns data cabling, connectivity, AV, access control and final testing? |
| Move and occupation | Are removals, temporary arrangements and staff induction included? |
| Risk and client costs | How are unresolved conditions, approvals, VAT and changes treated? |
Ask for a clear exclusions schedule. If IT is client supplied, for example, the contractor may provide containment and power while your technology team supplies equipment. Someone still needs to coordinate the interface.
Do not automatically add an allowance where it is already included. Equally, avoid assuming that an item is covered because it appears on a design drawing.
Which design decisions have the greatest effect on cost?
The number and type of enclosed rooms
Meeting rooms affect more than partition quantities. Their acoustic performance, ventilation, lighting and AV requirements can change the scope substantially.
Establish how many rooms are needed, their expected occupancy and whether conversations require privacy. A small video-call room and a formal boardroom should not carry the same specification by default.
Bespoke joinery and finishes
Custom reception desks, banquette seating and specialist finishes can contribute to a distinctive workplace. They also require design development, coordination and procurement time.
Protect the elements that serve a clear purpose. Where a standard product performs equally well, it may offer a simpler route to delivery and future replacement.
Building services and technology
A new layout should be coordinated with existing infrastructure before the design is fixed. Confirm the capacity and condition of services, together with any landlord restrictions on connecting to them.
For technology, specify the user experience first. Explain how people should join meetings, share content and move between work settings. This helps avoid buying equipment that does not solve the underlying need.
How to compare office fit-out quotations fairly
Issue the same brief, drawings and information to each tendering team. Request a consistent pricing breakdown and ask each contractor to identify assumptions and provisional allowances.
A useful comparison checks scope, quality, programme and responsibility alongside price. Investigate a large difference rather than immediately treating it as a saving.
For instance, one proposal may retain existing air conditioning subject to testing, while another includes replacement. Those proposals describe different projects until the underlying assumption is resolved.
Ask how design changes will be priced and approved. A low opening price provides limited certainty if the brief is still changing or important decisions remain outstanding.
A London project example: scope matters more than floor area alone
ODCreate’s Phaidon International project at Citypoint Tower combined a 42,000 sq ft workplace with technical systems, acoustic coordination and provision for future growth.
It illustrates the importance of linking the budget to operational requirements. Floor area gives a useful scale, but the mix of work settings and supporting infrastructure explains what must be delivered.
Published project values should not be converted into a current quote without understanding their date, contract scope and exclusions.
Office fit-out cost FAQs
Is a CAT A+ office always cheaper to occupy?
Not always. It may reduce initial construction if the existing layout and specification suit your business. If substantial alterations are needed, the benefit can narrow. Compare adaptation costs, furniture, technology and lease terms against an alternative space.
Does a fit-out price include design?
That depends on the appointment. In design and build, design responsibilities sit within the contractor’s agreed scope. Under a traditional route, the client typically appoints the design team separately. Ask exactly what is included rather than relying on the procurement label.
Can we get a fixed price before completing the design?
A price can be agreed against a defined scope, but unresolved information may be covered by qualifications or allowances. Understand those conditions and the change process. Greater design and survey certainty makes the basis of the price easier to assess.
How much should we allow for furniture?
Prepare a furniture schedule covering quantities, performance requirements and reuse opportunities. Price that schedule separately unless furniture is clearly included in the main proposal.
When should we review the budget?
Review it when the brief is agreed, after the layout and services strategy are developed, before contract award and whenever a material change is proposed. Each review should show the effect on the overall funding requirement.
Build a fit-out budget around your business
A useful budget is a clear account of what your office needs to do, what the building already provides and what must change.
Talk to ODGroup about your office fit-out requirements to establish the construction scope, key interfaces and delivery considerations before committing to a programme.