Refurbishing an occupied office: how to plan the works around your team

Back to Insights

Refurbishing an occupied office: how to plan the works around your team

An occupied office refurbishment requires two plans to work together: the construction programme and the plan for keeping the business operational. The office must remain usable for staff while the project team has the access, separation and time needed to deliver the work safely.

Remaining in occupation can be a practical option, but it should be tested before the programme is fixed. The extent of the works, shared services and the availability of temporary space will influence what can be achieved.

A clear sequence helps everyone understand where they will work, what will change and when decisions are needed.

Can your office remain occupied during refurbishment?

Start by assessing whether construction activities can be separated from the working office. Consider staff access, deliveries, waste removal, welfare facilities and the potential effects of dust, noise and vibration.

Shared infrastructure needs particular attention. Work inside one area can affect cooling, power, data or fire systems serving another. A partition line on a drawing does not necessarily create an independent construction zone.

Some activities may require an area to be temporarily vacated even where the wider office remains open. Surveys and intrusive investigations also need an appropriate plan.

The decision should follow a coordinated review by the project team and building management. It should not be based solely on whether enough desks appear to remain available.

Build the programme around business-critical activities

Ask each team when disruption would have the greatest impact. Financial reporting, recruitment campaigns, client events and technology releases can create periods when interruptions are particularly difficult.

Identify the services that must remain available and the people authorised to agree to interruptions. Record how much notice they require and what a successful restart looks like.

Business requirement Planning response
Confidential client meetings Maintain suitable rooms and visitor routes
Critical IT operations Agree isolation, migration, testing and recovery arrangements
Busy operational periods Coordinate disruptive work with the business calendar
Accessibility needs Check temporary as well as final routes and facilities
Regular staff attendance Plan work settings and communications for every phase

Resolve conflicts early. If a noisy activity cannot take place during normal office use, investigate permitted alternative hours and the associated cost, rather than assuming weekend working is available.

Create a phased office refurbishment plan

A phase should be a workable piece of the project, not simply a line dividing the floor into equal areas.

For each phase, define the working area, its access, the construction scope, the services affected and the conditions for handing it back. Explain how staff and materials move without interfering with one another.

Review the sequence with specialist contractors. Ceiling work, services modifications and finishes may need access beyond the room being refurbished.

Avoid designing the final office first and treating phasing as an afterthought. A minor layout adjustment may allow a much simpler delivery sequence, while a tightly interdependent design can make partial occupation difficult.

The programme should also include preparation and transition time between phases. Moving people, testing systems and resetting the construction boundary are real activities.

Make temporary swing space fit for work

Swing space is the area used by staff while their usual location is being refurbished. Its suitability affects the experience of the whole project.

Check desks, connectivity, meeting facilities, storage, accessibility and the ability to concentrate. A vacant room with furniture is not automatically a workable temporary office.

Allocate capacity against expected attendance and role requirements. Explain how teams book space, receive visitors and access support while they are temporarily displaced.

Plan the move in both directions. Equipment inventories, personal belongings and specialist setups need owners. Where temporary space is limited, test whether adjusted attendance or external accommodation is required.

Temporary arrangements should have a defined duration and a fallback if the next area is not ready as expected.

Manage noise, dust and building-service interruptions

The contractor’s approach should address containment, housekeeping, deliveries and the interfaces with occupied areas. These controls need to remain effective as the site boundary moves.

Agree a communication route for complaints and urgent issues. Staff should know whom to contact if conditions differ from what was promised.

For service interruptions, establish the affected systems, approval, notice period, isolation plan and restart checks. Confirm who must be present and what happens if testing identifies a problem.

Do not promise a disruption-free refurbishment. A more useful commitment is a clear plan, realistic notice and a prompt response when circumstances change.

Communicate changes before staff encounter them

Provide information that people can act on. Tell staff which areas are unavailable, where to work, how to enter the building and whether meeting or refreshment arrangements have changed.

Use a predictable update schedule, supported by direct notices for significant changes. A simple plan showing the current phase may be more useful than a lengthy construction report.

Managers should receive enough notice to organise their teams. Reception, facilities and IT need the same current information so that visitors and staff receive consistent guidance.

Keep communications accessible and avoid relying on signs at the point where a route is already closed.

An ODGroup example: phased refurbishment at Marks & Spencer

At Marks & Spencer in Paddington, ODInteriors refurbished approximately 240,000 sq ft across five phases. Swing space and planned staff moves allowed occupation to continue during the works.

The relevant lesson is that move management belongs inside the delivery programme. Each completed area enables the next stage, so readiness must include the systems and facilities people need to work.

Define readiness before each phased handover

Agree what must be complete before staff move into an area. Include testing, cleaning, access, usable welfare facilities, furniture, IT and instructions for operating new equipment.

Distinguish between minor outstanding items and issues that prevent safe or effective occupation. Record who will close out remaining work and how access will be arranged after staff return.

Ask for updated information as each phase is completed. Facilities teams need to understand the systems they are operating, even while the wider project continues.

Occupied office refurbishment FAQs

Is it cheaper to stay in the office during refurbishment?

Not necessarily. Remaining in occupation can introduce phasing, temporary protection and alternative working hours. Compare those costs with temporary accommodation and the disruption of moving out.

Can all noisy work happen at weekends?

That depends on permissions, building rules, neighbouring occupiers and contractor arrangements. Check the proposed hours early. Weekend working should be an agreed delivery assumption, not a promise made before investigation.

Do staff need to move out for surveys?

Some surveys are non-intrusive, while others require access or temporary vacancy. Where asbestos-related intrusive investigation is needed, specialist advice and appropriate arrangements are essential. Agree the survey scope before booking it.

Who should communicate with employees?

A nominated client contact should coordinate staff messages, supported by current information from the contractor and building management. This keeps operational instructions consistent.

How do we avoid moving teams repeatedly?

Develop the phasing plan around team needs and service dependencies. Compare the number of moves under different sequences. Fewer moves may be possible, but they must be balanced against available space and the overall programme.

Plan the works and the working day together

An occupied refurbishment succeeds when operational requirements are treated as part of the brief.

ODGroup’s office refurbishment team can help assess the building, phase the works and coordinate delivery around the people using the space.

 