Planning an office refurbishment between tenancies: a landlord’s guide

Back to Insights

Planning an office refurbishment between tenancies: a landlord’s guide

The period between tenants creates an opportunity to review how an office building serves the market. A coordinated approach to CAT A fit-out and landlord works can address the condition of vacant floors, shared facilities and building services, while preparing the asset for its next occupier.

The strongest brief starts with the intended letting offer. Reinstating the previous specification may be appropriate, but it should be a decision rather than the default.

Before stripping out the space, establish what can be retained, what needs investigation and which improvements support the building’s next phase.

Define the letting strategy before the refurbishment scope

Decide who the space is intended to attract and what those occupiers are likely to need.

A CAT A floor gives an incoming tenant scope to create its own workplace. A CAT A+ offer provides more of the fitted environment in advance. Subdivision, a whole-floor letting or a phased approach may each require different service and access arrangements.

Discuss these options with the leasing and professional teams. Avoid specifying a layout that depends on an untested assumption about the future occupier.

Set out the intended handover condition in practical terms: what is provided, what the tenant will add and how the building can accommodate change.

Assess the office condition before deciding what to remove

Review available drawings, maintenance information, commissioning records and the condition of existing installations. Arrange appropriate surveys where information is incomplete.

Create a record of elements that may be retained, refurbished, relocated or replaced. Raised floors, ceiling systems, partitions and furniture can have different prospects for reuse.

Do not assume an empty floor is fully understood. Hidden services, inaccessible areas and undocumented tenant alterations may affect the scope.

Keep the technical assessment separate from the legal and commercial treatment of the outgoing tenancy. Your property advisers should address lease obligations, while the project team establishes what work is needed to achieve the future brief.

Coordinate landlord works with the vacant-floor fit-out

An incoming occupier experiences the whole building, not just the demised floor. Reception, lifts, washrooms, access, end-of-journey facilities and shared services can influence how well the office functions.

Building element Refurbishment question
Office floors What specification and flexibility will the next occupier receive?
Reception and circulation Is access clear, practical and consistent with the offer?
Washrooms and amenities Are condition, capacity and accessibility suitable?
Building services Which systems need maintenance, adaptation or replacement?
External areas Are terraces, façades or entrances part of the scope?
Operations How will the completed building be managed and maintained?

Combining work packages may improve coordination, but it also creates dependencies. Replacing shared plant can affect tenants whose floors are outside the refurbishment area.

Agree those interfaces before fixing the programme and budget.

Choose a specification that supports future adaptation

A lettable office needs a clear specification, but excessive rigidity can create avoidable changes for the next tenant.

Consider how meeting rooms might be introduced, how services can be zoned and where future connections will be made. Record the capacity and limitations of the installations.

For CAT A+, select a layout that responds to the target market while retaining practical options for adaptation. Durability, replacement availability and maintenance access matter alongside appearance.

A small improvement to access or services coordination may offer more lasting value than a decorative element that is difficult to maintain.

Plan the programme around vacancy and access

Identify the earliest date each area becomes available and the dependencies before work can begin. Include surveys, design, approvals, procurement, construction and testing.

A vacant floor within an occupied building still needs an operational plan. Confirm access routes, delivery arrangements, noise-sensitive periods and the treatment of shared systems.

Where the letting programme requires early access or phased handover, define what that means. A viewing, tenant survey and construction mobilisation involve different levels of readiness and responsibility.

Keep the leasing team informed of the programme assumptions. Marketing dates should reflect the work required to provide the agreed specification.

Protect reuse opportunities before strip-out

A pre-refurbishment review should identify what has value before removal starts.

Record the condition, quantity and location of reusable items. Confirm whether they can remain in place, be reused elsewhere in the project or transferred to another use.

Coordinate dismantling, storage and protection with the programme. Reuse becomes harder if suitable materials are removed without identification or damaged before a destination is agreed.

Where retention is not appropriate, record why. Technical performance, compatibility and future maintenance all need to be considered alongside material savings.

ODGroup projects: different landlord requirements

  • At 129 Wilton Road, the refurbishment combined CAT A and CAT A+ floors with wider building improvements.
  • At 111 Buckingham Palace Road, ODInteriors returned a former CAT B floor to CAT A and delivered associated upgrades.

The projects illustrate why the future letting offer should guide the scope. The right intervention depends on what the next occupier will receive and how that relates to the rest of the building.

Reception area with timber feature wall, minimalist desk, and illuminated base detailing at 129 Wilton Road London by ODGroup.

Prepare a complete landlord handover

Define the information needed by building management and incoming occupiers before completion.

This may include coordinated as-built drawings, operating and maintenance information, testing records, warranties and details of interfaces for future tenant works.

Confirm who will manage outstanding items and how access will be arranged once the space is let. If a tenant fit-out begins soon after completion, agree the boundary between the two projects.

A clear handover reduces ambiguity about what has been provided and helps the next team plan its work.

Landlord office refurbishment FAQs

Should we always strip a vacant office back to CAT A?

No. Assess the existing fit-out, target occupier and letting strategy first. Some elements may support a fitted offer or be suitable for reuse. The decision should reflect the future brief and technical condition.

Is CAT A+ suitable for every building?

Not necessarily. It requires decisions about layout, equipment and occupation that may not suit all prospective tenants. Test the offer against the target market and the building’s constraints.

Can refurbishment proceed while other tenants remain?

Often, provided the works can be appropriately separated and shared services are managed. Review access, disruptive activities and interruptions with building management and the project team.

Should building services be replaced between tenancies?

That depends on condition, remaining service life, capacity and the intended specification. A survey-led assessment is more useful than replacing everything or retaining everything by default.

What should we provide to the incoming tenant?

A clear handover specification, relevant building information and requirements for future alterations. The precise documents depend on the project and occupation arrangements.

Prepare the building for its next occupier

A landlord refurbishment should connect the asset’s condition to a defined letting proposition.

ODGroup’s CAT A and landlord works team can help assess the scope and coordinate improvements across vacant floors, shared areas and building systems.

Get in touch to discuss your next project

Fill out the form and we’ll get back to you shortly.

  • This field is for validation purposes and should be left unchanged.

Related posts