Moco Museum
The details
- Location: One Marble Arch
- Value: £7,625,000
- Size: 25,000 sqft
- Duration: 24 weeks
Moco Museum – an independent art museum set to bring it’s unique and inspiring vision to visitors through its unparalleled collection of modern and contemporary pieces.
Founded in Amsterdam, the museum, having conquered Barcelona, has now turned its sights to London and this August celebrated the opening of their new flagship location at One Marble Arch.
The project involved a comprehensive technical design and construction fit out for the renowned modern and contemporary art museum at its new flagship location in London. We inherited the project at Stage 3, and developed it through Stage 4 to completion. The project was a CAT B shell and core fit out covering lower ground, ground and first floor spaces.
The team
- Client: Moco Museum
- Architect: Archer Humphreys Architects
- Project Manager: Gardiner & Theobald
- Cost Consultant: Gardiner & Theobald
- M&E Consultant: NDY
- Lighting Consultant: Hoare Lea
ODInteriors delivered:
- CAT A – shell and core fit out
- Mechanical and electrical
- MEPH including security system
- Fire alarm system
- IT systems
- Linking staircase
- New disabled access lift
- Public toilets
- Staff breakout area
- Bespoke art hatches for transfer of art
I had the privilege of working closely with ODInteriors and their dedicated team throughout this ambitious project, and despite the challenges of working within a compressed schedule, the team demonstrated an exceptional commitment to meeting our ambitious timeline.
We set a high bar for them, pushing the project forward at every step, and they responded with precision and professionalism.
Their dedication to the accelerated programme ensured we achieved our goal of opening as early as possible, delivering a remarkable space within a very short timeframe. They delivered not just a functional exhibition space, but one that reflects the very essence of the Moco brand.Birthe Faessen, Chief Exhibition, Collection, and Operating Officer Moco Museum
Key aspects of the project
It goes without saying that the aesthetic was key to Moco, building on the resounding success of its previous two locations, the London museum has been designed to elevate the existing building and significantly contribute to the local area.
Architectural designs were a collaboration between Archer Humphreys Architects and Moco Museum itself. With the interior space being moulded to the traditional look and feel of the existing Marble Arch building, whilst still exemplifying the renowned Moco brand. It was our task to execute these designs in time and on budget, with time being the prominent factor through the course of the works.
The client requested that the internal linking staircase act as a tie through the exhibition, providing visitors with a seamless transition throughout the space. While working within specific time and budget parameters, we successfully delivered the architectural focal point. Designed as a spiral, the staircase, crafted from steel and finished with high-quality timber treads, perfectly embodies the spirit of Moco, creating a functional and aesthetically pleasing transition between levels.
One design consideration that required further refinement was the thickness of the partition walls. Originally designed at a standard size, we recognised the need to make the walls thicker to convey a sense of permanence and substance. This was a deliberate decision on Moco’s part, adjusting the wall thickness aligned with their commitment to establish a lasting and impactful space.
Continuing with structural considerations, the weight of the art on the floor as well as walls and ceilings also had to be taken into account. A bespoke design of structural works had to be employed to accommodate certain works of art – brackets were incorporated into ceilings to support hanging art, and ‘heavy spots’ were installed to support different weight on the floor. These features were designed with longevity in mind, allowing art to be swapped and changed around in the future, not restricting the exhibition to its current state.
Challenges
One of the key elements to this project was the programme, we needed to reach project completion during the summer months to ensure the museum would be open to welcome the influx of visitors brought to the city due to school holidays and summer tourism. With a slightly later start date than intended, this was a factor in almost every decision made throughout the project.
Noisy work constraints were also a cause for concern. Originally agreed that we could carry out works as necessary, the landlord expressed concerns during the course of the project and so we had to renegotiate the timings of when noisy works could be carried out, adding further delay to the programme. However, we were able to establish a schedule that accommodated the landlord and building tenants whilst allowing the team to carry out the necessary works.
Due to this period of negotiation, along with some knock-on effects surrounding sprinkler delays, the programme was pushed back, with completion not being due until the beginning of September, a time period that did not suit our clients needs of a summer opening. And so we embarked upon an accelerated programme.
With effective site management and longer working hours, the team worked to bring the September date forward by a month, achieving project completion at the beginning of August.
Collaboration
The entire project operated on a very collaborative basis. We worked very closely with the client to deliver to their expectations on time, they were very much hands on with the project which led to a great working relationship.
We understood their requirements and appreciated that the programme required a summer completion and so we made this an absolute priority, as did the whole of the professional team involved. Cohesive working throughout, good communication and pride in delivering quality ensured all-round success.
The result
The result? A project delivered successfully on an accelerated programme that, despite a late start, completed earlier than anticipated, resulting in a very happy client and an exceptional space that perfectly frames the artwork and epitomises the Moco brand and everything they stand for.
Project Team
- ODInteriors
Mark Yates
Project Director, Core Projects
- ODInteriors
Mike Jones
Surveying Director, Core Projects
- ODInteriors
Steve Lamper
Senior Project Manager
- ODInteriors
Rhiana McAnnalley
Commercial Manager
- ODInteriors
Jo Campbell
Senior Design Manager
- ODInteriors
Louie Collinson
Technical Services Manager