Case studies

A true sign of success is a strong client list. From Rolls-Royce to Saatchi & Saatchi and the Royal Albert Hall, many of our clients are household names.

  • Hans 3
  • Hans 2
  • Hans 1
Back to Case Studies

Hans Cresent

Solutions Turnkey, London
34,000 ft2, £2.3m
2 Phase CAT B fitout and refurbishment

The details:

  • Designer: Od Solutions
  • Project Manager: Od Solutions
  • Duration: Phase 1 - 9 weeks, Phase 2 - 20 weeks

Works included:

  • New reception
  • New gymnasium
  • Male & female changing rooms
  • Atrium breakout space
  • Tailored furniture package
  • Supply and install partitioning & doors
  • Supply and install new floor coverings
  • Re-decorate all wall finishes and existing timber doors
  • Supply and Install new tea point
  • Carry of full validation of existing electrical services
  • Supply and install new modular light fittings in place of existing
  • Supply and install comms room cabinets and equipment
  • Provide Audio Visual Equipment within 2x Meeting Rooms
  • Validation of existing mechanical systems